Name | AKB |
Nationality | India |
PetitionType | Renewal |
Center | Nebraska Service Center-LIN |
Filing Date | May 8th, 2019 |
Status | Card Ordered |
Decision Date | Oct 1st, 2019 |
Processing Time | 146 days |
EAD Qualification Criteria | Current Approved I-140 |
Visa Status at Filing | H4 Visa |
Additional Info | Attorney |
H4 EAD Applying experience: | May 08 - Applied H1+H4+H4 EAD in PP May 17 - H1 Approved May 28 - Biometrics done Oct 01 - EAD status changed to "New Card Is Being Produced" I raised three expedite request. First on got rejected on 23rd. For the second one I got the response on Sept 9th as the case already assigned to an officer, so they cannot expedite it. For the third one got the response on Sept 27th as case already under review and then evening the case status changed to "received your response to our request for additional information" (but they never asked for any information). |
Created Date/Time | Apr 8th, 2019 13:07:56 |
Last Updated | Oct 1st, 2019 22:32:14 |